A Conversation with Walbridge on Quality, Rework and Wasted Time

Share:

Recently, at Advancing Data Center Construction West, Facility Grid CEO Daniel Russo sat down with Chris Morgan, Group Vice President of Walbridge, to discuss the intricacies of data center and mission critical construction, and the tools they trust to manage and execute these high-stakes, complex projects. The following includes Part 1 of their conversation, focusing on the importance of quality in construction, avoiding rework, and saving your team’s time.

Daniel Russo: We’ve had a long partnership together. We’re going to get into the topic of quality and through ready systems, talk a little bit about business risks and impact of mitigating those risks in data center construction.

Why don’t you tell us all about Walbridge?

Chris Morgan: Sure. Walbridge, we’ve been in business 110 years this month, actually, in March. We’re proud of that. We’re headquartered in Detroit, we have eight other offices in the US and one in Brazil.

ENR Rankings, we’re usually in the top 30, this year we’re 24 this year. #1 and #2 in auto and manufacturing, and #10 in the data center space.

Ten years ago, we didn’t do any work in data centers, it was what we called a playbook. It was a market we wanted to enter. We put a plan together and actually got a job at Microsoft, so thanks to Microsoft, because they brought us to this space.

Now we’re doing a lot of business in the data center space. Full service supplier from site selection to pre construction, engineering, and then we also get into facility management after a job’s complete, and sadly some of our older, aging markets we do demolitions of facilities that maybe we built 30 years ago. So full service.

Data center space again, just in the last 10 years it’s grown, it went from nothing 10 years ago to about 60% of our business. This year we’re doing $10 billion in revenue. So it’s been an incredible growth in market. We have approximately 50 builds of 50 gigawatts under construction or in development.

It’s a growing space that we all know we’re happy to be in it. It’s very selective, not everybody can do all these jobs.

Daniel: We’ve been working together for five years, it’s been a really strong and great partnership. Do you remember why you guys selected us and what you were looking for?

Chris: Yeah, we had a quality processor starter commissioning. It was Excel files, so you know QR maybe but just to a SharePoint. A very isolated, compartmentalized process. We saw we needed a broader platform to help us have more visibility of what we do.

You guys have been a great partner, and what I’d say about Facility Grid is, they listen to us. They tried to understand us first. They didn’t shove a technology down our throats telling us it’s the best thing since canned beer. Here you go. They really listen to us. So they found a way to work with us.

Daniel: Great. So let’s jump into the topic of quality. I hear a lot about projects that typically have about 30% rework, right? So delays, cost overages. Why is quality so important and how have you already built into your processes?

Chris: Quality is important. Anyone who’s been to any sessions today, it’s sort of about lack of resources,  stretched resources. Everybody’s run thin, from the subs to the owners, ourselves, commissioning agents. So you can’t afford to do things multiple times. And safety, the more times you go back and touch things, there’s a chance for safety.

To have to go back, it’s just problematic. So, you’ve got to avoid the rework.

Quality for us is trying to do it right the first time.

We learned quality from Toyota, one of the best companies, most disciplined, quality oriented companies in the world. We took their Kanban process, which is a four-step process for commissioning mechanical electrical equipment. We took it, with their permission, and called it our vStart Process. It was a very disciplined, step-by-step gated process, to sign off each phase, punch list each phase, identify damage of each phase. So the client can say right then on the truck, ‘nope, send it back’ or ‘yeah, it’s cosmetic’ or you know accept it, vs. waiting to the end.

So it’s very important to us. We recognize we owe a client a quality job.

Daniel: How much time do you think you guys spend in building that process in each project?

Chris: How much time do we spend on each job in quality? I’d say it’s a third to 40% of our team’s jobs. So much of what we do is quality, right? It might not be the physical checking a box, but it ‘s being involved in the submittal phase. Is it the right submittal? Is it the right thing? Is it coordinated all the way through?

You know, a field startup team checking on things, with physical startups. It’s a big chunk of our time, it’s a big chunk of ourselves, our owners, and our partners on the job.

Daniel: Talk me through the ROIs of spending that amount of time. Is it rework? Is it time saved?

Chris: Sadly, it’s a hidden cost. You had a chart earlier that showed how Facility Grid tied together a lot of the projects, pieces, parts, and teams. There’s probably 10 circles on that slide. So, for a simple one piece of equipment that has to get signed off, whatever stage of installation or construction, there might be 10 people involved.

There’s 1,500 pieces of equipment, so start doing the math. 450 of them got to get looked at more than once, 10 people, two hours, you added up to $100-$150 an hour, you’ll get millions of dollars in just lost cost.

You don’t necessarily see it in change order. You don’t necessarily see it as wasted cost. It’s wasted time. We’re a big proponent of lean practices and one of the forms of waste in lean is wasted resources and waiting.