Bridging Commissioning and Operations in Higher Education Facilities: CxEnergy Session Recap

Share:

After years of supporting higher education construction projects, we know well the considerations and complexities involved in commissioning for a university building. Across campuses large and small, we’ve seen commissioning trends unique to university projects that can make a big difference for long-term operational success.

At CxEnergy 2026, we were proud to present with Michael Hoffman, Energy Manager at University of Arizona, on “Bridging Commissioning and Operations in Higher Education Facilities.” Facility Grid’s Joe Pascal joined Michael to share what he’s learned from higher education construction teams and how to apply these practices to any campus.  

Here’s a look at what we discussed:

Commissioning Beyond Project Completion

Commissioning outcomes directly influence how effectively facilities teams can operate, maintain, and adapt buildings over time. On college campuses, facilities teams must:

  • Maintain system performance over decades of operation
  • Support complex environments such as laboratories, research spaces, and classrooms
  • Adapt buildings to evolving academic and research needs
  • Operate large portfolios with limited staff and resources

Getting All Your Stakeholders On the Same Page

Large university facilities projects, given their size and scope, often involve coordinating and aligning multiple teams of people, each with a different objective:

  • Planning, design, and construction teams
  • Facilities management and maintenance
  • Energy management teams
  • Environmental health and safety
  • Occupants and users (students, faculty, researchers, community)

As these groups interact with the building at different stages of its lifecycle, many rely on the success of commissioning outcomes, though they don’t directly participate in the commissioning process.

Owner Project Requirements (OPR): The Goal

All commissioning standards and guidelines are built around the assumption of a clear OPR, serving as the reference point for the entire project. The Owner Project Requirements (OPR) document defines:

  • Operational goals for the building
  • Performance expectations
  • System functionality and priorities
  • How systems should be tested and delivered
  • Modularity and flexibility in operational uses and capacity

Beyond commissioning, the OPR should guide how the building is designed, constructed, tested, and operated.

Higher Ed Owner Project Requirements (OPR): The Reality

Unfortunately, though the OPR should be seen as a necessary aspect of a building process, we’ve heard from teams who say they’ve often asked mid design or construction phase, “Where is the OPR?” Instead of receiving the official OPR, commissioning agents are given related documents, like design specs, an RFP, or project programming docs. However, these are not the same as a clearly defined OPR.

Without a clear OPR:

  • Testing objectives can be unclear
  • Operational expectations may be undefined
  • Commissioning focuses on verifying design rather than the owner’s long-term goals

Using Monitoring Tools to Support Commissioning

In some projects, monitoring tools such as fault detection and diagnostics (FDD), ad-hoc building automation networks and Automated Commissioning (AutoCx) are implemented early in the project lifecycle. This creates a bridge between commissioning activities and long-term building operations.

When introduced during construction or startup phases, these tools can help:

  • Identify system issues earlier
  • Observe system behavior under real operating conditions
  • Support Functional Performance Testing
  • Assist with integrated system testing

What Leading Universities Do Differently

Many higher education institutions are evolving their commissioning programs to be more efficient with fewer errors and less paperwork. Common approaches we’ve seen include:

  • Standardizing commissioning scope and procurement processes
  • Standardized commissioning process documentation across projects
  • Linking commissioning with energy management systems
  • Formalizing monitoring-based commissioning programs
  • Using commissioning data to inform capital planning

We’ve noticed universities in particular also have the advantage of getting support from their peers—other universities. Teams across the country talk with one another to share lessons learned and help each other out, comparing strategies and collaborating through higher ed commissioning cohorts. This camaraderie amongst higher education facilities teams helps prevent mistakes and encourages best practices, and creates a standard of commissioning across all campuses.

Long-Term Impact of Successful Cx on Campus Operations

Though just one aspect of a building project, commissioning does in fact affect a building as a whole, even after it’s in operation. When commissioning information supports operations effectively, facilities teams have seen the difference in:

  • Maximized system performance over longer effective lifecycles
  • Issues identified earlier – Predictive vs. Reactive maintenance
  • Maintained operational tempo even in face of declining resources
  • Preservation of institutional knowledge between projects