Building with Confidence: Digitizing Quality and Commissioning for High-Stakes Projects

Share:

In high‑stakes construction—hospitals, labs, manufacturing, data centers, airports—delays are expensive, and risk tolerance is low. Joe Pascal of Facility Grid sat down with Brian Stark and Andy Bretherick from Industrial Project Innovation (IPI) to discuss how digitizing quality and commissioning moved them beyond spreadsheets, streamlined field workflows, and gave teams the data to reduce rework, speed turnover, and make faster, informed decisions.


Joe: For folks who don’t know you yet—who is IPI?

Brian: I’m Brian Stark, Vice President and Business Unit Director at IPI. We incorporated in 2016. By 2020, we had 100 teammates on board, and by 2024 we’d managed upwards of $13 billion of work. Our services span framing, project planning, estimating, procurement, construction management, controls, and commissioning.

Andy: I’m Andy Bretherick, Commissioning Manager at IPI. I have been MEP startup and commissioning manager for over 20 years. Started out in the Electrical side of construction early.


Joe: In the world of mission‑critical builds, precision and timing are non‑negotiable. What did “quality” look like for you before—and what changed?

Brian: Historically, commissioning was a struggle—getting a job commissioned properly and turning it over to meet client expectations. With Facility Grid, we finally have a system that, used properly, eliminates surprises, gives us confidence in our data, and keeps us operating in a continuous‑improvement mindset.

Andy: Everyone knows the pain of Excel sheets and email chains—sometimes you have the document you need; sometimes you don’t. That leads to missed inspections, delayed tests, breaker trips not set because no one can find the coordination study, and the list goes on. Facility Grid became our safety net. It helps our teammates understand each task within the sequence of operations as the project is built. Our approach is operational readiness commissioning, from procurement through functional testing.


Joe: Why was change necessary?

Brian: Things felt disjointed. Communication was a challenge, and we lacked a real‑time understanding of where we were in the commissioning process.

Andy: We started by tightening our front‑end documents—tweaking owner‑provided specs, rewriting SOWs, clarifying roles and responsibilities for the joint venture (JV) and subs. There’s no easy button, so we made sure tasks were clear and expectations aligned.


Joe: What goals guided your move to technology?

Andy: Clarity and accountability. We wanted owners to trust the information they were getting, no matter the owner’s style. Adoption was the big hurdle, so ease of use mattered. That’s why Facility Grid stood out—the transition from Excel/macros to software was actually smooth.

Brian: Not every owner is equally sophisticated. We needed a one‑stop shop that puts information in a digestible form for clients without forcing us to juggle multiple systems.


Joe: There are a lot of tools you could have chosen. Why Facility Grid?

Andy: The issue resolution workflow is outstanding. We even use Facility Grid for building QA/QC, things like scratches on walls or waterproofing, throughout construction. People think it’s “just commissioning software.” It’s not. It’s adaptable. If you’re a data contractor, you could track every cable if you wanted.

Brian: For me, the selling point was the one‑stop shop. We needed it for commissioning, but we also adapted it for QA functions and asset tracking. We didn’t want two or three different tools.

Andy: It also exports reliability information straight into owner systems—Maximo, etc.—as a mass download. That handoff is easy. The biggest for use was meeting the owners’ cyber security protocols. Facility Grid met all security protocols for our owners. 


Joe: Adoption can make or break a rollout. How did you get diverse teams on board?

Andy: Subs sometimes resist new tools, until they try it. We use QR codes on assets tied to our visual control process (we model after Kanban, ProTag, G‑comply). In the field, you open the camera, scan, and you’re in; one or two taps to open checklists, create issues, add photos, or close tasks. It works where they work—phones and iPads. Once teams see how easy it is, they want to use it.

Andy: It’s not just contractors; owners love it too. I watched a maintenance tech download the boiler O&M from the asset QR code multiple times. When I checked in, he said it was faster than using his own system.


Joe: How does Facility Grid change day‑to‑day management?

Andy: It gets us out of spreadsheets. Instead of separate issue, activity, documentation, and schedule logs, everything lives in one place. In weekly meetings, we pull up the dashboards and see, in real time, what’s done and what’s not. The asset list shows percentage complete for checklists, functional tests, open issues—everything we need.

Brian: It’s a real‑time snapshot of our quality and commissioning effort.


Joe: Let’s talk schedule. How do you stay ahead of plan slippage?

Andy: Two ways. We can link P6 (or another project schedule), and we can schedule at the asset level. We assign dates per step per asset, which lets us plan months ahead. Facility Grid overlays actual activity on the schedule, so we see where we’re ahead or behind and can reallocate resources before something becomes critical.


Joe: Lots of tools “track issues.” What’s unique about how Facility Grid handles resolution and communication?

Andy: It’s asset‑centric. We assign issues directly to the responsible contractor, notify inspectors and watchers, and automate reporting—end of day or instantly on upload. Deadlines trigger alerts when they’re missed. It’s hard to ignore an issue when it’s tied to the actual equipment you’re responsible for.

Brian: Could we track issues in Procore? Sure. But Procore isn’t commissioning‑centric. Facility Grid combines asset‑based commissioning with issue tracking—so we don’t need two platforms. Our JV partners even started pulling the same detailed contractor reports themselves after seeing the value.


Joe: Closeout is where many teams struggle. What changed for you?

Brian: Closeout starts on day one. With Facility Grid, documents are captured and validated as we go. It’s transparent and accountable. When turnover comes, we’re not scrambling.

Andy: Only a few people can delete documents, so the record is reliable. The final download can be big, depending on project size, but it’s complete and categorized to the asset level. Maintenance and reliability teams can open an asset and see observations, issues, startup history—the gold you need for the lifecycle.

Brian: It’s real time, not six months after completion, so facilities teams can start preventive maintenance immediately.


Joe: Sum it up—what’s the business impact of Facility Grid for IPI?

Brian: Better cross‑team coordination and executive‑level visibility. I can review dashboards and answer client questions about commissioning status with certainty.

Andy: Clarity of roles and dates, tighter teamwork, and earlier problem‑solving. It helps you turn a C‑team into an A‑team because everyone can see what’s next and what’s blocking.

Brian: And we’ve seen tangible ROI—issue resolution cycles dropped from six weeks to about two and a half, even with some long‑lead assets in the mix.


Joe: Final thoughts for teams evaluating solutions?

Andy: Pick a platform that adapts to your process instead of forcing you to change it. Make it easy for people in the field to participate.

Brian: Aim for a single source of truth that’s commissioning‑ready from day one. The rest—clarity, accountability, predictable turnover—follows.