At Facility Grid, we’ve seen how commissioning trends in higher education building projects can impact long-term operations. At CxEnergy 2026, Facility Grid’s Joe Pascal presented with Michael Hoffman, Energy Manager at University of Arizona, on “Bridging Commissioning and Operations in Higher Education Facilities.” Here is Part 1 of our session recap:
Michael Hoffman: I’m the Campus Energy manager with the University of Arizona in Tucson. My role includes all of our strategic energy management initiatives, metering and instrumentation on our district energy loop, commissioning, retrocommissioning, fault detection, energy analytics, and whatever else the bosses tell me they need in the middle of the day.
But for your purposes, I am the owners rep at the UOVA for all of our new construction, retrofit, recommissioning, retrocommissioning, continuous base commissioning. I’ve been in the industry in one form or another for about 26 years.
Evolution of Commissioning Technology
Joe Pascal: Let’s start with commissioning. We know it’s been evolving over the years to what it is today. There’s more visibility tools out there, more structure, definitely better communication and opportunity to consolidate everything seem as source of truth. Michael, how does technology now compare to the way things used to be?
Michael: When this industry really picked up, you know, 20-25 years ago, was when commissioning really started to get gas in the engine.
It was treated as an overlay, right? It was, “we’re designing and building a building and, different markets had different reasons, we need or we want to commission it.” And so, we as commissioning providers or representatives were a square peg fitting into a round hole usually at the 11th hour.
A lot of my work as an independent commissioning agent was in military construction. And I remember buying 4-inch binders in bulk and printing out a trove of checklists and leaving them with the GC. And then you get the call, we’re out at the 11th hour, you need to be in here for functional testing. And you get there and the book has barely been touched. Checklists are half-filled out, there’s duct work still hanging open, the hot water system is complete except for xyz, and there’s no continuity. Even more important, what I’ve learned from the owner side, especially in higher ed, is not only is there no continuity but the work product of the commissioning process ends up landing on deaf ears.
One of the reasons we’re in business is because we know that the information about how the building’s designed, what’s been spec’d, what’s been installed, and how does it work, is ongoing information. It should be a tool for my colleagues doing Operations and Maintenance. And at that stage back in the day, it wasn’t a tool. It was just another binder that was collecting dust until it became a CD that was collecting dust and then a jump drive and now it’s collecting virtual dust on somebody’s server.
And even to this day, the challenge is, from the owner side, how do we use this information? It’s certainly not going to work in a book of paper checklists. The electronic software now finally gives you as the commissioning providers, and me as the owner who’s interested in the commissioning process, an opportunity to bring that information forward and use it live in an ongoing operational and maintenance model. That’s where the big difference is now with electronic commissioning processes.
What Happens Once a Building is in Use?
Joe: So, you know, commissioning doesn’t end at turnover. It’s really where the value begins, right? And, you know, the commissioning deliverables—the question is, do they actually support operations long term? Michael, can you talk about what happens once buildings are actually in use?
Michael: Everybody’s heard the phrase “day two issues,” right? It’s kind of the rationale for the industry. When I first started at the University of Arizona in 2017, we had planning and design and construction as its own silo, with its own AVP doing what they had to do to meet their goals. And we had facilities management with its own AVP trying to meet our goals. And never the twain shall meet.
There was a constant struggle. And it’s where higher ed functions (or malfunctions) differently than many other verticals where you are engaged. One thing I hope to help with is a better understanding of what you’re dealing with in higher ed facilities and organizational structures.
When a building is complete, it’s not complete. Our buildings, especially in higher ed, we don’t knock stuff down. Buildings are going to stand virtually in perpetuity. My colleagues and I are, to this day, running 100+ year-old buildings, and trying to work at current requirements with current codes, utility capacities, and operational needs.
If I don’t know how that building was supposed to start in the beginning and be functioning at the outset, I’m stuck—or I have to reiterate and recommission buildings just to understand where I’m at.
At UVA, we have a 24-month warranty period. We hold contractors accountable for two years, but during that time we have to be relatively hands-off, because anything we do could potentially violate or invalidate the warranty. So, now we’re really two years post-occupancy before we really wrap our arms around it. At that point, it’s almost like a brand-new building again. By Year Two, that’s when we’re really first taking that building under full ownership, and it’s a brand new day.
One of the values of commissioning is if the commissioning record is live and dynamic and can be used recursively by O&M staff, then that continuity becomes a lot cleaner. Even two years after a warranty, I know how the building is supposed to operate and I know what problems were found at the onset, at pre-functional performance or integrated testing, and now I’m not starting from a brand new day trying to figure out a two-year-old building with no contractual support.
Joe: I completely agree. Across campuses, we consistently see variability from project to project. Every project delivers information differently, and from an operational perspective, every building has its own playbook. So, does your team have a standard way to understand system readiness across all buildings?
Getting a Consensus on What Readiness Actually Means
Michael: Yes, depending on who you ask and how they defines readiness. You’ve got architects, engineers, general contractors, owners, and a slew of other stakeholders, and each entity defines what substantial readiness is, and they don’t overlap.
The architect is concerned with, do I have my signage, my lighting, is it presentable, is it attractive? Is it the building that we want people to engage with? And the engineer is going, is the hot water system hot? The owner is going, what am I supposed to do with this building?
The whole commissioning process is to bring everybody to the table and have a consensus on what is operationally ready: when is this building ready to occupy? When is it ready to function?
Coming from a commissioning background, and being in the owner’s camp, I’m trying to push this concept that the building is not ready until the commissioning agent tells you it’s ready. Because if the contractor says they’re finished, and the subs are wrapping up, and the air handlers haven’t been commissioned, and the hot water system isn’t balanced right—the building may look ready, but I can’t put people in the building. And in higher ed, moreso than many other industries, if you can’t deliver to your customers, they’ll let you know.
Readiness, in my mind and my team’s mind, is based on the commissioning agent. Can you tell me that you, as a professional in the commissioning services, are confident that I can take the keys and run this building the way I’m expecting to run it?
Joe: And there are a lot of constituents across the universities, right? They’re uniquely complex. You’ve got Research, Health Care, Student Life, and they’re all relying on the systems to perform as they’re designed, right? But the problem is many of the stakeholders aren’t part of the commissioning process.
What user groups need to be engaged in the commissioning process for it to be successful?
Commissioning Agents Should Be Main Link in the Communication Chain
Michael: Far more than typically are. At the University of Arizona, I’ve got virtually every type of facility. We just built a new nano-chip fabrication facility for research in the electrical computer engineering building. We have dormitories, office buildings, academic laboratories for teaching and research separately, athletics, the whole slew. The horizontal gamut of who has a stake in a building being designed and installed and functional runs really wide.
As commissioning providers, when you look at this gamut of stakeholders, you have to be black box communicators. The commissioning agent needs to understand what we do as far as the technical, but also needs to be able to output it in language other stakeholders understand.
When you’re working with higher ed, you have to remember you’re working with people. Higher ed owners want you to tell them when something doesn’t look right early on. We can only fight the battles we can see, and we can’t see everything. As the commissioning provider, even if it’s outside the typical scope, you have the vantage point of being able to bring things around and be that communication chain, and keep issues prioritized and keep the dialogue consensual where everyone is weighed in. That’s the biggest thing with the breadth of stakeholders.