Mission Critical Projects: How to Prevent Small Delays from Snowballing into Costly Disruptions

Share:

With the fast pace and complexity of mission critical projects, like data centers, airports, and hospitals, no issue is too small to address—because minor delays can cascade into weeks of schedule disruptions.   

Small missteps often begin with an oversight as simple as a late vendor delivery, but with mission critical work, these oversights can quickly turn into costly delays. 

To prevent small issues from snowballing, it’s essential to track project components as early as possible and at the lowest level. In the high-stakes environment of data centers, communication between all systems must be constant and transparent.

Let Past Missteps Inform Future Projects

When beginning a new project, it’s crucial to have a comprehensive overview of past projects, so you can learn from prior missteps and know what to avoid. 

This is where a centralized platform with a digital history of prior projects is critical, so all participants can view and identify past issues to prevent them in future projects. 

It’s okay to make mistakes, but with easy access to project history, there’s no reason to make the same mistake twice. 

Complete Quality Control Before Commissioning Starts 

When quality control is not complete before commissioning starts, commissioning becomes a troubleshooting process instead of a validation of the success of the quality control. 

Not completing quality control prior to the commissioning stage is one of the biggest challenges we see on mission critical projects. This forces Cx teams to fix problems instead of those problems being caught earlier in the QC process.

Ensuring all systems, processes, and personnel are completely prepared, safe, effective, and set up for success in the very beginning will mitigate future risks and prevent costly delays, so the commissioning process isn’t bogged down by addressing QC issues. 

One of the fastest growing mission critical industries is data centers. The emergence of artificial intelligence (AI) and the Internet of Things (IoT) is translating into a growing demand for data centers, driving development. McKinsey & Company projected the data center industry will grow 10% a year through 2030, with global spending on the construction of new facilities hitting $49 billion. As timelines get shorter and pressure to deliver builds, teams will need to think differently about how they deliver operationally ready data centers to market on time. Learn more about ensuring operational readiness for data centers in our eBook here.

Close the Documentation Gap 

Without proper documentation, it’s difficult to prove the readiness of facilities to stakeholders and ensure that the QC completion is validated by the Cx process. Organizing your documents in one centralized location not only ensures operational readiness but also prevents rework later. 

When your entire project team works in one software, all the gaps that may occur on the project become easily visible and are caught early. 

With mission critical work like data center construction, operational readiness can’t be skipped—as being fully prepared prior to Day One can be the difference between the success or failure of a project.