At CxEnergy 2026, Facility Grid’s Joe Pascal presented with Michael Hoffman, Energy Manager at University of Arizona, on “Bridging Commissioning and Operations in Higher Education Facilities.” Here is Part 2 of our session recap, where they discuss the importance of procuring commissioning early on for higher education projects, and how standardization can set apart the quality of work of commissioning agents.
Joe: One of the challenges really with commissioning is timing because a lot of times commissioning enters often after the key decisions have been already made. It means that the operational expectations might be applied and not defined. And it makes it harder to operate or to set the operational expectations clearly.
Michael, why is it so difficult to bring commissioning in?
Michael: Procurement, procurement, procurement. The money that is budgeted for a project may not come to bear until a point beyond when the commissioning agent should be on board.
If you think the first person you need to hire for a project is the architect, you’re wrong. You need the commissioning agent. Commissioning is more of the concept [of a project] than just the brick and mortar.
The whole focus of commissioning is to keep the end in mind. But that needs to start up front, and one of the biggest challenges that we have is OPRs to fill in the parenthesis.
There are different ways that we procure at the University. For example, oftentimes the commissioning agents funding is built into the project. If it’s built into the design project, then I can get the money a little earlier, but it’s going to run out before construction because the design team may not have a scope or they will not fund the design phase all the way through construction. If it’s funded in construction, then I can’t release the money until the GC has been awarded and now we’re late in the game.
You Won’t Regret Finding Money for the Commissioning Agent
If I tell my administration I need the commissioning agent on early and they say how are you going to select them? I’m going to take them to consultant selection as long as they’re on my list. I still got to fight for the funding. I still got to find some source.
This is the biggest challenge for getting commissioning agents on early because the money has to come from somewhere. If it’s project money, you got to wait for the project. If it’s utilities money, I can’t get the project to cover it. So now I’m reaching into budgetary money rather than pulling it out of a bonding structure.
People don’t want to spend money out of their own budget, especially if they don’t truly understand the value. Which goes back to teaching senior leadership about why commissioning is as imperative and integral as it is. Because then I can say, “We need the commissioning agent.” I want them to go, “Oh, yeah, you’re right. We need the commissioning agent. I will find the money.” That’s the ultimate answer, “I will find the money. Go select your commissioning agent.” Happens very rarely.
Standardize Now, Thank Yourself Later
Joe: Michael, how important is consistency across buildings for your team?
Michael: It’s imperative to us because, I come from commissioning, so I know the value of this deliverable and I know that I want to use it, but it’s very hard for me to deploy it to my colleagues and my teams if every building has a different deliverable. We’re all kind of doing the same thing. We all bring different expertise, different experiences, but let’s face it, a pre-functional checklist is a pre-functional checklist.
Ideally I want to be able to point to a library and it doesn’t matter what building on campus, but when the mechanic or the BAS tech or the plumber or an engineer comes in to do a new project and wants to understand the commissioning record, he or she can go to that library and find the same stuff in every folder. They don’t have to wonder, was this building done on paper checklist, and this one was done in this software, so I got to remember how do I find it in this software? Standardization.
And I have a feeling that the commissioning industry may be a little wary of this concept of standardization horizontally because you feel like maybe it boxes you in and takes away your individual value proposition. I’m here to tell you that’s not the case.
Your Value as a Cx Agent is in How You Communicate
We know facilities professionals, we know who our go-to commissioning professionals are, and it’s not because of how well you write a report. It’s not because your checklist had 18 more lines than the other guy’s checklist. We know you guys by the expertise, by the unique experience, by the ability to communicate and carry that consensus moving forward. By standardizing, you’re allowing us to consume your commissioning record more readily and easily, without just looking like the other person.
I have multiple commissioning agents that use electronic software and I don’t think of them in terms of, oh he’s a Facility Grid guy, or he’s a paper checklist guy—I go, this is the guy that found the problem and was able to communicate it early enough so it was no longer a problem, and this is the guy that showed up in the dark at night, checked off some checklists and sent me a report two days later on an issue that should have been taken care of yesterday.
That’s the difference. Standardization only allows you to more readily deliver what we can consume.